Krell v Henry (1903) CA
Case Summary:
Krell v Henry established a key principle in contract law regarding frustration. The plaintiff rented a flat to the defendant specifically for viewing King Edward VII's coronation procession. The coronation was postponed, rendering the purpose of the contract impossible. The defendant refused to pay the remaining balance. The court held that the contract was frustrated; both parties were discharged from their obligations, and the plaintiff could not recover the unpaid amount.
Key Findings & Principles:
  • Frustration: The contract was frustrated because the unforeseen postponement of the coronation made the contract's fundamental purpose impossible to achieve. This was the foundation of the agreement, even though the coronation wasn't explicitly mentioned in writing.
  • Impossibility: The impossibility doesn't require the direct subject matter of the contract (the flat itself) to cease to exist. Instead, a state of things or condition essential to the contract's performance (viewing the coronation) must become impossible. This expands the scope of frustration beyond situations where the subject matter is destroyed. This builds upon the precedent set in Taylor v Caldwell.
  • Contemplation: The impossibility must be something neither party could have reasonably foreseen or contemplated at the time the contract was made.
  • Criticism: The Privy Council in Maritime National Fish Ltd v Ocean Trawlers Ltd expressed reservations about the broad interpretation of Krell v Henry, suggesting its application should be limited and not readily extended to similar cases. This highlights the need for careful consideration of the specific facts when applying the principle of frustration.
Comparison to Taylor v Caldwell:
Krell v Henry builds upon Taylor v Caldwell, expanding the concept of frustration beyond the destruction of the subject matter of the contract. While Taylor v Caldwell focuses on the physical impossibility of performance due to the destruction of the thing itself (a music hall), Krell v Henry extends frustration to cases where an essential, albeit non-physical, element of the contract becomes impossible.
Points to Remember for Exams:
  • Distinguishing Feature: The key distinction in Krell v Henry lies in the focus on the purpose of the contract – viewing the coronation – rather than the mere existence of the subject matter (the flat). This is crucial for applying the doctrine of frustration.
  • Limitations: Be aware of the limitations highlighted by Maritime National Fish Ltd v Ocean Trawlers Ltd. Krell v Henry should not be applied broadly; it is a fact-specific case.
  • Application: To successfully argue frustration, you must show that:
    1. An unexpected event occurred.
    2. The event rendered performance impossible or radically different from what was contemplated.
    3. The event was not foreseeable by either party at the time of contract formation.
    4. The event made the fundamental purpose of the contract impossible to achieve.
Further Research: Review the cases of Taylor v Caldwell and Maritime National Fish Ltd v Ocean Trawlers Ltd to further understand the principles of frustration and the limitations of Krell v Henry. Consider how these cases differ in their application of the doctrine.